PK0-005 · Question #330
During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?
The correct answer is D. Scrum. Scrum is an agile methodology well-suited for projects that require frequent milestone deliveries and functionality demonstrations. It emphasizes iterative development, with regular presentations to stakeholders, which aligns with CompTIA Project+ principles for agile project…
Question
During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?
Options
- AWaterfall
- BSDLC
- CXP
- DScrum
How the community answered
(18 responses)- A6% (1)
- C11% (2)
- D83% (15)
Explanation
Scrum is an agile methodology well-suited for projects that require frequent milestone deliveries and functionality demonstrations. It emphasizes iterative development, with regular presentations to stakeholders, which aligns with CompTIA Project+ principles for agile project management.