During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

The correct answer is D. Scrum. Scrum is an agile methodology well-suited for projects that require frequent milestone deliveries and functionality demonstrations. It emphasizes iterative development, with regular presentations to stakeholders, which aligns with CompTIA Project+ principles for agile project…

Project Management Concepts

Question

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Options

  • AWaterfall
  • BSDLC
  • CXP
  • DScrum

How the community answered

(18 responses)
  • A
    6% (1)
  • C
    11% (2)
  • D
    83% (15)

Explanation

Scrum is an agile methodology well-suited for projects that require frequent milestone deliveries and functionality demonstrations. It emphasizes iterative development, with regular presentations to stakeholders, which aligns with CompTIA Project+ principles for agile project management.

Topics

#Project methodologies#Agile Scrum#Iterative development#Stakeholder communication