Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as…

The correct answer is C. Performance feedback. The survey is intended to gather feedback and insights from stakeholders about the project's successes, shortcomings, and potential areas for improvement. This feedback can be used to inform performance feedback for individual team members and help the project team identify…

Project Management Concepts

Question

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

Options

  • ADaily stand-up
  • BProject momentum
  • CPerformance feedback
  • DMeeting minutes

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    85% (17)

Explanation

The survey is intended to gather feedback and insights from stakeholders about the project's successes, shortcomings, and potential areas for improvement. This feedback can be used to inform performance feedback for individual team members and help the project team identify areas where they can improve their processes or approaches.

Topics

#Stakeholder feedback#Team performance#Continuous improvement#Lessons learned