PK0-005 · Question #51
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance…
The correct answer is C. Hold sessions to understand user challenges. E. Log the issue in the project risk register. To address user reluctance towards a new system, the project manager should hold sessions to understand user challenges and formally log this significant adoption issue in the project risk register.
Question
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)
Options
- ATrain users on the proper use of the system.
- BEscalate the issue to the CCB.
- CHold sessions to understand user challenges.
- DTrack system usage and report user activity.
- ELog the issue in the project risk register.
- FCreate a memorandum of acceptable use.
How the community answered
(51 responses)- A12% (6)
- B8% (4)
- C75% (38)
- D4% (2)
- F2% (1)
Why each option
To address user reluctance towards a new system, the project manager should hold sessions to understand user challenges and formally log this significant adoption issue in the project risk register.
Training users is a common step, but it typically comes after understanding why they are reluctant; if the training doesn't address their specific challenges, it may not resolve the underlying adoption issue.
Escalating to the Change Control Board (CCB) is premature; the CCB deals with formal change requests, not initial assessment of user adoption problems.
Holding sessions directly with users, such as workshops or focus groups, is a proactive way to gather feedback, understand their specific pain points, concerns, and reasons for reluctance regarding the new CRM system, which is essential for developing effective adoption strategies.
Tracking system usage provides metrics but does not help understand the 'why' behind low adoption, which is the core problem described.
User reluctance that jeopardizes project success is a significant potential threat to project objectives, making it a risk that must be formally identified, documented in the project risk register, and subsequently analyzed for potential mitigation strategies.
Creating a memorandum of acceptable use is a policy document, not a direct action to understand or gain acceptance for a system where users are already reluctant.
Concept tested: Stakeholder engagement, risk identification, and change management