A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after…

The correct answer is B. Cadence. Cadence refers to establishing a repeatable, consistent rhythm for activities, such as the scheduling of tasks and deliverables. By implementing a cadence, the team creates a regular, predictable flow after each iteration, which helps streamline the process and maintain…

Project Management Concepts

Question

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options

  • ATask log
  • BCadence
  • CMilestones
  • DWork breakdown structure

How the community answered

(54 responses)
  • A
    2% (1)
  • B
    91% (49)
  • C
    2% (1)
  • D
    6% (3)

Explanation

Cadence refers to establishing a repeatable, consistent rhythm for activities, such as the scheduling of tasks and deliverables. By implementing a cadence, the team creates a regular, predictable flow after each iteration, which helps streamline the process and maintain consistency throughout the project. This ensures that tasks and deliverables follow a set rhythm, improving efficiency and planning.

Topics

#Agile Planning#Cadence#Project Scheduling#Consistent Flow