PK0-005 · Question #326
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after…
The correct answer is B. Cadence. Cadence refers to establishing a repeatable, consistent rhythm for activities, such as the scheduling of tasks and deliverables. By implementing a cadence, the team creates a regular, predictable flow after each iteration, which helps streamline the process and maintain…
Question
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
Options
- ATask log
- BCadence
- CMilestones
- DWork breakdown structure
How the community answered
(54 responses)- A2% (1)
- B91% (49)
- C2% (1)
- D6% (3)
Explanation
Cadence refers to establishing a repeatable, consistent rhythm for activities, such as the scheduling of tasks and deliverables. By implementing a cadence, the team creates a regular, predictable flow after each iteration, which helps streamline the process and maintain consistency throughout the project. This ensures that tasks and deliverables follow a set rhythm, improving efficiency and planning.
Topics
Community Discussion
No community discussion yet for this question.