The correct answer is B: Project Gantt. The Project Gantt chart is a scheduling tool used to track task progress and timelines. When tasks are completed ahead of schedule, updating the Gantt chart ensures accurate tracking.

Tools and documentation

Question

A project manager provided details regarding the completion of the following tasks: - Vendor selection took less time than planned. - Equipment procurement took less time than estimated. - Equipment installation went according to schedule. Which of the following should the project manager update?

Options

  • AChange log
  • BProject Gantt
  • CIssue log
  • DRequirements traceability matrix

Explanation

The Project Gantt chart is a scheduling tool used to track task progress and timelines. When tasks are completed ahead of schedule, updating the Gantt chart ensures accurate tracking.