PK0-005 · Question #344
A project manager provided details regarding the completion of the following tasks: - Vendor selection took less time than planned. - Equipment procurement took less time than estimated. - Equipment…
The correct answer is B. Project Gantt. The Project Gantt chart is a scheduling tool used to track task progress and timelines. When tasks are completed ahead of schedule, updating the Gantt chart ensures accurate tracking.
Tools and documentation
Question
A project manager provided details regarding the completion of the following tasks:
- Vendor selection took less time than planned.
- Equipment procurement took less time than estimated.
- Equipment installation went according to schedule.
Which of the following should the project manager update?
Options
- AChange log
- BProject Gantt
- CIssue log
- DRequirements traceability matrix
How the community answered
(26 responses)- A4% (1)
- B73% (19)
- C15% (4)
- D8% (2)
Explanation
The Project Gantt chart is a scheduling tool used to track task progress and timelines. When tasks are completed ahead of schedule, updating the Gantt chart ensures accurate tracking.
Topics
#Gantt chart#Schedule management#Progress tracking#Project updates