A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria…

The correct answer is B. Project sponsor. The project sponsor is responsible for defining the success criteria for the project. The sponsor typically has the authority and responsibility to determine the overall objectives, expected outcomes, and key performance indicators (KPIs) for the project, which are used to…

Project Management Concepts

Question

A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?

Options

  • ALead architect
  • BProject sponsor
  • CProgram manager
  • DScrum master

How the community answered

(53 responses)
  • B
    94% (50)
  • C
    2% (1)
  • D
    4% (2)

Explanation

The project sponsor is responsible for defining the success criteria for the project. The sponsor typically has the authority and responsibility to determine the overall objectives, expected outcomes, and key performance indicators (KPIs) for the project, which are used to evaluate its The project manager works with the sponsor to ensure these criteria are clear and aligned with the project's goals.

Topics

#Project Charter#Success Criteria#Project Sponsor#Project Manager Roles