PK0-005 · Question #333
A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable…
The correct answer is D. Some stakeholders might not be completely satisfied. When a project manager achieves a compromise, it often means that stakeholders may not be entirely satisfied with the outcome. However, compromise is sometimes necessary to balance differing needs, consistent with CompTIA Project+ principles on stakeholder management and
Question
A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?
Options
- AToo much time might be spent generating project delays.
- BThe project manager might be seen as weak.
- CThe number of change requests throughout the project might be reduced.
- DSome stakeholders might not be completely satisfied.
How the community answered
(18 responses)- A11% (2)
- B6% (1)
- C6% (1)
- D78% (14)
Explanation
When a project manager achieves a compromise, it often means that stakeholders may not be entirely satisfied with the outcome. However, compromise is sometimes necessary to balance differing needs, consistent with CompTIA Project+ principles on stakeholder management and