A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable…

The correct answer is D. Some stakeholders might not be completely satisfied. When a project manager achieves a compromise, it often means that stakeholders may not be entirely satisfied with the outcome. However, compromise is sometimes necessary to balance differing needs, consistent with CompTIA Project+ principles on stakeholder management and

Project Management Concepts

Question

A project manager has received different functional requests from three individual stakeholders. The project manager is able to have all parties concede somewhat in order to find a reasonable solution. Which of the following outcomes would most likely occur?

Options

  • AToo much time might be spent generating project delays.
  • BThe project manager might be seen as weak.
  • CThe number of change requests throughout the project might be reduced.
  • DSome stakeholders might not be completely satisfied.

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    6% (1)
  • C
    6% (1)
  • D
    78% (14)

Explanation

When a project manager achieves a compromise, it often means that stakeholders may not be entirely satisfied with the outcome. However, compromise is sometimes necessary to balance differing needs, consistent with CompTIA Project+ principles on stakeholder management and

Topics

#Stakeholder management#Conflict resolution#Negotiation#Compromise