nerdexam
CompTIA

PK0-005 · Question #359

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

The correct answer is D. Planning. The correct answer is D. Establishing accepted communication channels and defining access requirements are planning activities. These outputs - typically captured in a Communications Management Plan and resource/access plan - are created during the Planning phase, where the PM…

Project Life Cycle Phases

Question

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

Options

  • ADiscovery
  • BExecution
  • CInitiating
  • DPlanning

How the community answered

(27 responses)
  • B
    4% (1)
  • C
    4% (1)
  • D
    93% (25)

Explanation

The correct answer is D. Establishing accepted communication channels and defining access requirements are planning activities. These outputs - typically captured in a Communications Management Plan and resource/access plan - are created during the Planning phase, where the PM defines how the project will be executed, monitored, and controlled. Discovery (A) is an informal pre-project or requirements gathering phase. Execution (B) is when the work defined in the plans is carried out. Initiating (C) focuses on authorizing the project and identifying key stakeholders, not defining detailed communication or access protocols.

Topics

#Communication planning#Access management#Project life cycle phases#Planning phase

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice