PK0-005 · Question #358
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
The correct answer is C. Precedence diagramming method. The correct answer is C. The Precedence Diagramming Method (PDM) is the standard technique for building a project network diagram that shows logical dependencies between activities (e.g., Finish-to-Start, Start-to-Start). It is specifically designed for creating schedules that…
Question
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
Options
- AWaterfall method
- BSimulation method
- CPrecedence diagramming method
- DCost ratio analysis
How the community answered
(42 responses)- A5% (2)
- B2% (1)
- C93% (39)
Explanation
The correct answer is C. The Precedence Diagramming Method (PDM) is the standard technique for building a project network diagram that shows logical dependencies between activities (e.g., Finish-to-Start, Start-to-Start). It is specifically designed for creating schedules that reflect task sequencing and dependencies. The Waterfall method (A) is a project lifecycle methodology, not a scheduling tool. The Simulation method (B) (e.g., Monte Carlo) is used for risk and schedule risk analysis. Cost ratio analysis (D) is a vendor evaluation and cost estimation technique.
Topics