PK0-005 · Question #347
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
The correct answer is D. Defect log. A Defect Log is specifically used to track and manage any defects or bugs identified within a project. This log helps document details about the defects, their status, severity, and resolution process. Since the sponsor is asking for a log listing bugs identified within the…
Question
A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?
Options
- AChange log
- BIssue log
- CRisk register
- DDefect log
How the community answered
(26 responses)- B8% (2)
- C4% (1)
- D88% (23)
Explanation
A Defect Log is specifically used to track and manage any defects or bugs identified within a project. This log helps document details about the defects, their status, severity, and resolution process. Since the sponsor is asking for a log listing bugs identified within the project, the Defect Log is the most appropriate tool.