The correct answer is B: Apply the contingency plan.. To mitigate the risk of data theft by hackers, the contingency plan should be applied. A contingency plan is designed to handle unforeseen issues or risks that could impact the project, such as a data breach. It typically includes steps to respond to security threats, minimize da
Question
Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?
Options
- AUpdate the issue log.
- BApply the contingency plan.
- CTransfer the risk.
- DSubmit a change request.
Explanation
To mitigate the risk of data theft by hackers, the contingency plan should be applied. A contingency plan is designed to handle unforeseen issues or risks that could impact the project, such as a data breach. It typically includes steps to respond to security threats, minimize damage, and restore systems.
Topics
Community Discussion
No community discussion yet for this question.