PK0-005 · Question #352
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the…
The correct answer is A. Risk. The project manager should use the Risk log to capture concerns about potentially losing team members due to a stressful work environment. The Risk log is used to document potential issues that may occur in the future, such as the risk of losing team members, and outline…
Question
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
Options
- ARisk
- BChange
- CDefect
- DIssue
How the community answered
(29 responses)- A72% (21)
- B7% (2)
- C17% (5)
- D3% (1)
Explanation
The project manager should use the Risk log to capture concerns about potentially losing team members due to a stressful work environment. The Risk log is used to document potential issues that may occur in the future, such as the risk of losing team members, and outline strategies for mitigating or managing those risks.
Topics