A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

The correct answer is B. Downtime window schedule. The correct answer is B. A downtime window is a pre-scheduled period during which a system can be taken offline or transitioned to a new state (go-live) with minimal disruption to normal business operations. Coordinating this window with business stakeholders is exactly what…

Project Management Concepts

Question

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

Options

  • AValidation check
  • BDowntime window schedule
  • CCustomer notifications
  • DRisk analysis

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    73% (19)
  • C
    4% (1)
  • D
    8% (2)

Explanation

The correct answer is B. A downtime window is a pre-scheduled period during which a system can be taken offline or transitioned to a new state (go-live) with minimal disruption to normal business operations. Coordinating this window with business stakeholders is exactly what the PM is doing. A validation check (A) is a testing activity. Customer notifications (C) are a communication task that would follow once the window is defined. A risk analysis (D) is an analytical activity, not a scheduling coordination meeting.