PK0-005 · Question #353
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
The correct answer is B. Downtime window schedule. The correct answer is B. A downtime window is a pre-scheduled period during which a system can be taken offline or transitioned to a new state (go-live) with minimal disruption to normal business operations. Coordinating this window with business stakeholders is exactly what…
Question
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
Options
- AValidation check
- BDowntime window schedule
- CCustomer notifications
- DRisk analysis
How the community answered
(26 responses)- A15% (4)
- B73% (19)
- C4% (1)
- D8% (2)
Explanation
The correct answer is B. A downtime window is a pre-scheduled period during which a system can be taken offline or transitioned to a new state (go-live) with minimal disruption to normal business operations. Coordinating this window with business stakeholders is exactly what the PM is doing. A validation check (A) is a testing activity. Customer notifications (C) are a communication task that would follow once the window is defined. A risk analysis (D) is an analytical activity, not a scheduling coordination meeting.