PK0-005 · Question #356
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project…
The correct answer is C. Closing contracts. Since all invoices have been paid and the vendor has completed the work, the project manager's objective for the meeting is likely to close contracts. This involves formally concluding the contractual obligations, ensuring all terms are met, and completing any necessary…
Question
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?
Options
- AReassigning resources
- BRemoving access
- CClosing contracts
- DEvaluating the project
How the community answered
(15 responses)- A7% (1)
- C87% (13)
- D7% (1)
Explanation
Since all invoices have been paid and the vendor has completed the work, the project manager's objective for the meeting is likely to close contracts. This involves formally concluding the contractual obligations, ensuring all terms are met, and completing any necessary paperwork to officially close out the contract with the vendor.