Question

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

Options

  • AStatus report
  • BIssue log
  • CRisk report
  • DRisk register