PK0-005 · Question #362

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

The correct answer is D. RACI. A RACI matrix (Responsible, Accountable, Consulted, Informed) is specifically designed to define and communicate roles and responsibilities across a project. It clearly maps which stakeholders are Responsible for doing the work, who is Accountable (ultimate owner), who should…

Tools and documentation

Question

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

Options

  • AConcept of operations
  • BWBS
  • CIntegrated master schedule
  • DRACI

How the community answered

(28 responses)
  • A
    4% (1)
  • C
    4% (1)
  • D
    93% (26)

Explanation

A RACI matrix (Responsible, Accountable, Consulted, Informed) is specifically designed to define and communicate roles and responsibilities across a project. It clearly maps which stakeholders are Responsible for doing the work, who is Accountable (ultimate owner), who should be Consulted (two-way communication), and who needs to be Informed (one-way communication). This makes it the ideal artifact for determining who to communicate with and at what level of engagement. A WBS defines work scope, an Integrated Master Schedule tracks timing, and a Concept of Operations describes how a system will work - none of these define communication stakeholders and levels.

Topics

#RACI matrix#Communication planning#Stakeholder management#Project artifacts