PK0-005 · Question #321
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of…
The correct answer is B. Business case. The business case is used to document the business reasons and benefits of the project. It provides justification for the project, outlining its objectives, expected benefits, and how it aligns with the organization's strategic goals. The business case is typically submitted…
Question
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
Options
- AStatement of work
- BBusiness case
- CRequirements document
- DWork breakdown structure
How the community answered
(36 responses)- A3% (1)
- B89% (32)
- C6% (2)
- D3% (1)
Explanation
The business case is used to document the business reasons and benefits of the project. It provides justification for the project, outlining its objectives, expected benefits, and how it aligns with the organization's strategic goals. The business case is typically submitted for approval before the project is formally initiated.