nerdexam
CompTIACompTIA

PK0-005 · Question #320

PK0-005 Question #320: Real Exam Question with Answer & Explanation

The correct answer is D: Apply contingency buffers to the critical path.. Adding contingency buffers to the critical path is a method to account for potential delays, increasing project certainty.

Project Management Concepts

Question

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options

  • AHold a new backlog prioritization meeting.
  • BAdd milestones to check the project's progress.
  • CAdjust the task relationship to complete coding in advance.
  • DApply contingency buffers to the critical path.

Explanation

Adding contingency buffers to the critical path is a method to account for potential delays, increasing project certainty.

Topics

#Risk Management#Schedule Management#Contingency Planning#Critical Path

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions