CompTIACompTIA
PK0-005 · Question #320
PK0-005 Question #320: Real Exam Question with Answer & Explanation
The correct answer is D: Apply contingency buffers to the critical path.. Adding contingency buffers to the critical path is a method to account for potential delays, increasing project certainty.
Project Management Concepts
Question
During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?
Options
- AHold a new backlog prioritization meeting.
- BAdd milestones to check the project's progress.
- CAdjust the task relationship to complete coding in advance.
- DApply contingency buffers to the critical path.
Explanation
Adding contingency buffers to the critical path is a method to account for potential delays, increasing project certainty.
Topics
#Risk Management#Schedule Management#Contingency Planning#Critical Path
Community Discussion
No community discussion yet for this question.