PK0-005 · Question #339
PK0-005 Question #339: Real Exam Question with Answer & Explanation
The correct answer is D: Communication plan. The communication plan outlines how updates should be sent regarding deliverables, including who the recipients are, the frequency of updates, the format, and the channels to be used. It ensures that information is communicated effectively and consistently to all relevant stakeho
Question
Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
Options
- ADashboard
- BStatus report
- CMeeting minutes
- DCommunication plan
Explanation
The communication plan outlines how updates should be sent regarding deliverables, including who the recipients are, the frequency of updates, the format, and the channels to be used. It ensures that information is communicated effectively and consistently to all relevant stakeholders.