The correct answer is A: Obtain project sign-off.. Obtaining project sign-off is crucial in the closure phase, as it signifies formal acceptance of the project deliverables by the stakeholders.
Project Life Cycle Phases
Question
Which of the following is the most important activity for the project manager during the closure of a project?
Options
- AObtain project sign-off.
- BCapture lessons learned.
- CDocument historical information.
- DRelease resources.
Explanation
Obtaining project sign-off is crucial in the closure phase, as it signifies formal acceptance of the project deliverables by the stakeholders.
Topics
#Project Closure#Project Manager Responsibilities#Project Sign-off#Project Life Cycle