PK0-005 · Question #350

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

The correct answer is A. Rollback plan. A rollback plan is designed to remove a new package and revert to the previous one if the new package fails during a smoke test. This plan ensures that in the event of issues during testing, the system can return to its previous stable state, minimizing downtime and maintaining…

Project Management Concepts

Question

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

Options

  • ARollback plan
  • BDowntime stage
  • CMaintenance window
  • DValidation checks

How the community answered

(19 responses)
  • A
    89% (17)
  • B
    5% (1)
  • D
    5% (1)

Explanation

A rollback plan is designed to remove a new package and revert to the previous one if the new package fails during a smoke test. This plan ensures that in the event of issues during testing, the system can return to its previous stable state, minimizing downtime and maintaining system

Topics

#Rollback plan#Software deployment#Smoke testing#Contingency planning