CAPM Practice Questions
535 real CAPM exam questions with expert-verified answers and explanations. Page 10 of 11.
- Question #451Adaptive Frameworks/Methodologies
A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?
Agile SchedulingIterative DevelopmentBacklog Management - Question #452Project Management Fundamentals and Core Concepts
What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?
Project Management HierarchyPortfolios Programs ProjectsStakeholdersResources - Question #453Predictive, Plan-Based Methodologies
A project team identifies defects that will require a modification to a tool's functionality. What process should the project manager follow to obtain stakeholder buy-in?
Change ControlIntegrated Change ControlProject Management Processes - Question #454Predictive, Plan-Based Methodologies
What key component of the project charter defines the conditions for dosing a project phase?
Project CharterExit CriteriaPhase ClosureProject Initiation - Question #455Business Analysis Frameworks
A business analyst is evaluating solutions against the expected results and logging defects along the way. The next task is to analyze the discrepancies prior to facilitating a go/...
Business AnalysisRequirements ElicitationProblem IdentificationSolution Evaluation - Question #456Business Analysis Frameworks
A business analyst is looking to uncover the root cause of a specific problem. What technique should the business analyst apply first?
Root Cause AnalysisBusiness Analysis TechniquesElicitation TechniquesWorkshops - Question #457Agile Frameworks/Methodologies
Which is the most accurate description of a backlog in agile?
Agile BacklogProduct BacklogAgile PrinciplesValue Prioritization - Question #458Project Management Fundamentals and Core Concepts
What is the process of determining the stakeholders impacted by a business problem or opportunity?
Stakeholder ManagementIdentify StakeholdersProject PlanningProject Management Processes - Question #459Adaptive Frameworks/Methodologies
A project manager joined a company to replace someone that left the project. There was no hand over, but the previous project manager developed a detailed schedule for the project...
Project delivery methodsAdaptive approachesTeam integrationUncertainty management - Question #460Predictive, Plan-Based Methodologies
An organization's annual report indicates that there needs to be a new strategy that prioritizes long-term goals and repetitive solutions. What project methodology should this orga...
Project methodologiesPredictive methodologyMethodology selection criteria - Question #461Predictive, Plan-Based Methodologies
A project team member is reviewing the scope of a task with an end user and realizes that requirements have changed. Which project artifact should be used in this situation?
Change ManagementProject Management PlanScope ManagementRequirements Management - Question #462Agile Frameworks/Methodologies
How should the product owner prioritize a list of tasks to be accomplished?
Product OwnerPrioritizationBusiness ValueAgile Principles - Question #463Project Management Fundamentals and Core Concepts
Vicus (team member) mentions they do not have enough market information to make proper decisions. Verma (agile facilitator) confirms it is because no one on the team understands th...
Issue ManagementProject DocumentationProblem IdentificationAgile Context - Question #464Predictive, Plan-Based Methodologies
A new project manager has been assigned to an ongoing project. What will the project manager use to identify the responsibilities of the stakeholders in the project?
Responsibility Assignment MatrixStakeholder ResponsibilitiesResource ManagementProject Planning - Question #465Agile Frameworks/Methodologies
A backwards path calculation estimates that the last work package will be completed 24 days from this coming Monday. The scrum team operates in two-week sprints. How many sprints a...
Agile estimationSprint lengthIteration managementSchedule calculation - Question #466Predictive, Plan-Based Methodologies
A project manager is working on a project that is in the planning stage. In order to show the project's progress to the sponsor, the project manager will track significant events i...
MilestonesProject PlanningProgress TrackingSchedule Management - Question #467Agile Frameworks/Methodologies
In an agile project, when should story prioritization be performed?
Agile PrioritizationProduct Backlog ManagementAgile PrinciplesContinuous Prioritization - Question #468Project Management Fundamentals and Core Concepts
The project manager needs to communicate a large amount of information to a large group of people. The project manager achieves this by using an intranet, knowledge repository, and...
Communication ManagementCommunication TypesPull CommunicationCommunication Channels - Question #469Predictive, Plan-Based Methodologies
An obstacle has been identified and could potentially hinder the project's progress. Where should this obstacle be documented?
Risk ManagementRisk RegisterProject DocumentsThreats - Question #470Predictive, Plan-Based Methodologies
A project has encountered some difficulties that will impact the project management plan and the project management process. Which two actions should the project manager take? (Cho...
Change ManagementChange RequestIntegrated Change ControlProject Management Plan - Question #471Adaptive Frameworks/Methodologies
A new vendor offers a one-time price break but cannot guarantee they will still be in the local market for any future projects. Which project management approach should be used to...
Hybrid Project ManagementProject Management MethodologiesRisk & Opportunity Management - Question #472Agile Frameworks/Methodologies
A program consists of four agile teams. Each team has a separate daily standup. Later each day, there is another standup meeting attended by one member from each team. Which Scrum...
Scrum of ScrumsScaled AgileTeam CoordinationDaily Scrum - Question #473Business Analysis Frameworks
What is the next step for a business analyst after the stakeholders have validated the requirements?
Requirements ManagementRequirements Traceability MatrixBusiness Analyst RoleValidation - Question #474Predictive, Plan-Based Methodologies
After a project meeting, Joe (project manager) finds out that some of the resources are not 100% committed to his project and this is causing delays in some project activities. Wha...
Resource ManagementStakeholder ManagementConflict ResolutionProblem Solving - Question #475Project Management Fundamentals and Core Concepts
Which life cycle does the level of formality for a solution documentation depend on?
Portfolio ManagementDocumentation StandardsGovernanceLife Cycles - Question #476Business Analysis Frameworks
While gathering nonfunctional requirements for developing a portal, which three aspects should a business analyst check to ensure that the solution developed will be fit for use by...
Nonfunctional requirementsRequirements gatheringBusiness analysisUsability - Question #477Agile Frameworks/Methodologies
A business manager has an idea for a new product they feel will be highly profitable to the business. How can the product idea be validated in the market before developing the prod...
Product ValidationPrototypingCustomer FeedbackMarket Validation - Question #478Agile Frameworks/Methodologies
A Scrumban team member wants to know what work has been completed this week. Which chart should the team member review?
Agile MetricsBurndown ChartScrumbanProgress Tracking - Question #479Predictive, Plan-Based Methodologies
In which project performance domain is the work breakdown structure (WBS) developed?
Work Breakdown StructurePlanning Performance DomainScope ManagementPMBOK 7 - Question #480Agile Frameworks/Methodologies
Which two techniques should be used to improve a process or product? (Choose two.)
Continuous ImprovementProcess ImprovementLessons LearnedRetrospective - Question #481Agile Frameworks/Methodologies
An agile team adds a user story related to architecture improvement in the current iteration. The product owner is not pleased, but the team says it must be added to the current it...
Agile Team ResponsibilitiesProduct Owner RoleTechnical DebtAgile Risk Management - Question #482Predictive Plan-Based Methodologies
What is the projected annual yield of a project investment, incorporating both initial and ongoing costs into the estimated percentage growth rate that the project will have?
Internal Rate of ReturnFinancial AnalysisProject SelectionInvestment Appraisal - Question #483Predictive, Plan-Based Methodologies
Calculate the cost variance, given the following: EV = 19 and AC = 23
Cost VarianceEarned Value ManagementProject Cost ManagementPerformance Measurement - Question #484Agile Frameworks/Methodologies
A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team's workflow at any moment, the project manager will need to re...
KanbanWIP limitsFlow managementAgile methodologies - Question #485Predictive, Plan-Based Methodologies
A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a...
Traditional Project ManagementPredictive Life CycleLinear ApproachProject Characteristics - Question #486Predictive Plan-Based Methodologies
If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?
Earned Value Management (EVM)Variance AnalysisProject Cost ManagementPerformance Measurement - Question #487Predictive, Plan-Based Methodologies
A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical proj...
Resource ManagementProject PlanningRoles and ResponsibilitiesAcquiring Resources - Question #488Predictive, Plan-Based Methodologies
Which three processes are generally included in risk management? (Choose three.)
Risk Management ProcessesPMBOKProject Management Knowledge Areas - Question #489Project Management Fundamentals and Core Concepts
A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit m...
Conflict ResolutionStakeholder ManagementCommunicationAcceptance Criteria - Question #490Predictive, Plan-Based Methodologies
HOTSPOT Question Based on the network diagram, which path is the longest?
Network DiagramCritical Path MethodPath AnalysisSchedule Management - Question #491Project Management Fundamentals and Core Concepts
Which characteristic defines the Delphi technique of group decision-making?
Delphi techniqueGroup decision-makingExpert judgmentProject management techniques - Question #492Business Analysis Frameworks
Which is a method of prototyping that creates a functioning representation of the final finished product to the user?
PrototypingHigh-fidelity prototypingRequirements validationSolution design - Question #493Predictive, Plan-Based Methodologies
A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usag...
Testing techniquesSolution validationUser acceptance testingQuality assurance - Question #494Project Management Fundamentals and Core Concepts
During the execution phase of a multibillion-dollar project, the project manager encountered performance issues with some of the team members. In a performance review meeting, the...
SMART objectivesGoal settingTeam performance managementProject execution - Question #495Predictive, Plan-Based Methodologies
As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperf...
Team Performance ManagementCommunication ManagementMonitoring & ControllingIssue Prevention - Question #496Adaptive Frameworks/Methodologies
The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will tak...
Adaptive Project ManagementProject ForecastingAgile MetricsVelocity and Cycle Time - Question #497Adaptive Frameworks/Methodologies
Which of the following projects is a quality candidate for adaptive approaches?
Adaptive approachesProject suitabilityMethodology selection - Question #498Project Management Fundamentals and Core Concepts
Leadership and management are often used interchangeably. Which of the following is leadership more involved in?
LeadershipPower and InfluenceLeadership vs. ManagementProject Leadership - Question #499Adaptive Frameworks/Methodologies
A project sponsor has requested a clear delivery roadmap for the implementation of a complex system that does not have clear and stable requirements. How should the team address th...
Release PlanningAdaptive PlanningUnstable RequirementsProject Roadmapping - Question #500Project Management Fundamentals and Core Concepts
Which project document is used to respond to and provide information on threats and opportunities that may impact project execution?
Risk ManagementRisk RegisterProject DocumentsRisk Responses