PMIPMI
CAPM · Question #468
CAPM Question #468: Real Exam Question with Answer & Explanation
The correct answer is B: Pull. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
The project manager needs to communicate a large amount of information to a large group of people. The project manager achieves this by using an intranet, knowledge repository, and e-learning tools. What kind of communication is being used?
Options
- APush
- BPull
- CInteractive
- DInterpersonal
Topics
#Communication Management#Communication Types#Pull Communication#Communication Channels
Community Discussion
No community discussion yet for this question.