CAPM · Question #469
An obstacle has been identified and could potentially hinder the project's progress. Where should this obstacle be documented?
The correct answer is D. Risk register. An obstacle that could potentially hinder project progress is a risk - specifically a threat. The risk register is the designated repository for documenting identified risks, including their descriptions, probability, impact, and planned responses. The stakeholder register (A)…
Question
Options
- AStakeholder register
- BCommunications management plan
- CAssumption log
- DRisk register
How the community answered
(25 responses)- A4% (1)
- B8% (2)
- D88% (22)
Explanation
An obstacle that could potentially hinder project progress is a risk - specifically a threat. The risk register is the designated repository for documenting identified risks, including their descriptions, probability, impact, and planned responses. The stakeholder register (A) tracks stakeholder information and engagement. The communications management plan (B) outlines how project communications will be handled. The assumption log (C) records assumptions and constraints made during planning - not potential threats to progress.
Topics
Community Discussion
No community discussion yet for this question.