An obstacle has been identified and could potentially hinder the project's progress. Where should this obstacle be documented?

The correct answer is D. Risk register. An obstacle that could potentially hinder project progress is a risk - specifically a threat. The risk register is the designated repository for documenting identified risks, including their descriptions, probability, impact, and planned responses. The stakeholder register (A)…

Predictive, Plan-Based Methodologies

Question

An obstacle has been identified and could potentially hinder the project's progress. Where should this obstacle be documented?

Options

  • AStakeholder register
  • BCommunications management plan
  • CAssumption log
  • DRisk register

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    8% (2)
  • D
    88% (22)

Explanation

An obstacle that could potentially hinder project progress is a risk - specifically a threat. The risk register is the designated repository for documenting identified risks, including their descriptions, probability, impact, and planned responses. The stakeholder register (A) tracks stakeholder information and engagement. The communications management plan (B) outlines how project communications will be handled. The assumption log (C) records assumptions and constraints made during planning - not potential threats to progress.

Topics

#Risk Management#Risk Register#Project Documents#Threats