A project has encountered some difficulties that will impact the project management plan and the project management process. Which two actions should the project manager take? (Choose two.)

The correct answer is B. Submit a change request. D. Perform integrated change control.. When difficulties arise that impact the project management plan, the correct procedure follows PMI's change management process: first, the project manager submits a change request (B) to formally document the needed adjustment. Then, perform integrated change control (D) to evalu

Predictive, Plan-Based Methodologies

Question

A project has encountered some difficulties that will impact the project management plan and the project management process. Which two actions should the project manager take? (Choose two.)

Options

  • APerform quality management.
  • BSubmit a change request.
  • CPerform a risk analysis.
  • DPerform integrated change control.
  • EPerform integrated project management.

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    76% (22)
  • C
    14% (4)
  • E
    7% (2)

Explanation

When difficulties arise that impact the project management plan, the correct procedure follows PMI's change management process: first, the project manager submits a change request (B) to formally document the needed adjustment. Then, perform integrated change control (D) to evaluate, approve, or reject that change request, ensuring all impacts across the project are assessed holistically before any changes are made. Quality management (A) addresses product/process quality, not plan changes. A risk analysis (C) may have preceded identifying the issue, but it is not the response action. 'Integrated project management' (E) is not a defined PMI process.

Topics