nerdexam
PMIPMI

CAPM · Question #489

CAPM Question #489: Real Exam Question with Answer & Explanation

The correct answer is D: Organize a meeting between the two managers.. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout. What should the project manager do?

Options

  • AAsk the project team to resolve all of the open issues.
  • BEscalate the issue to the project management office (PMO).
  • CEscalate to the sponsor to decide when to commence the rollout.
  • DOrganize a meeting between the two managers.

Topics

#Conflict Resolution#Stakeholder Management#Communication#Acceptance Criteria

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions