nerdexam
PMIPMI

CAPM · Question #490

CAPM Question #490: Real Exam Question with Answer & Explanation

To determine the longest path, we need to calculate the sum of durations for all possible paths from the start node (A) to the end nodes (J or K). The numbers on the arrows represent the duration of each activity. Possible paths and their durations: 1. A → B → C → F → I → K: 3 +

Predictive, Plan-Based Methodologies

Question

HOTSPOT Question Based on the network diagram, which path is the longest?

Explanation

To determine the longest path, we need to calculate the sum of durations for all possible paths from the start node (A) to the end nodes (J or K). The numbers on the arrows represent the duration of each activity.

Possible paths and their durations:

  1. A → B → C → F → I → K: 3 + 2 + 3 + 7 + 2 = 17
  2. A → B → D → G → J: 3 + 5 + 5 + 2 = 15
  3. A → B → E → H → J: 3 + 7 + 3 + 2 = 15

Comparing the durations, the longest path is A-B-C-F-I-K with a total duration of 17.

Topics

#Network Diagram#Critical Path Method#Path Analysis#Schedule Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions