The correct answer is A: Identify Risks. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which three processes are generally included in risk management? (Choose three.)

Options

  • AIdentify Risks
  • BMonitor Risk Costs
  • CPerform Qualitative Risk Analysis
  • DPlan Risk Responses
  • EEstimate Risk Activity Resources

Topics

#Risk Management Processes#PMBOK#Project Management Knowledge Areas