nerdexam
PMI

CAPM · Question #488

Which three processes are generally included in risk management? (Choose three.)

The correct answer is A. Identify Risks C. Perform Qualitative Risk Analysis D. Plan Risk Responses. PMBOK defines seven risk management processes; the three listed in the correct answer - Identify Risks, Perform Qualitative Risk Analysis, and Plan Risk Responses - are among the core recognized processes.

Predictive, Plan-Based Methodologies

Question

Which three processes are generally included in risk management? (Choose three.)

Options

  • AIdentify Risks
  • BMonitor Risk Costs
  • CPerform Qualitative Risk Analysis
  • DPlan Risk Responses
  • EEstimate Risk Activity Resources

How the community answered

(44 responses)
  • A
    89% (39)
  • B
    5% (2)
  • E
    7% (3)

Why each option

PMBOK defines seven risk management processes; the three listed in the correct answer - Identify Risks, Perform Qualitative Risk Analysis, and Plan Risk Responses - are among the core recognized processes.

AIdentify RisksCorrect

Identify Risks is the formal process of documenting which risks may affect the project and recording their characteristics in the risk register.

BMonitor Risk Costs

Monitor Risk Costs is not a recognized PMBOK process; the correct ongoing process is 'Monitor Risks,' which tracks identified risks and identifies new ones.

CPerform Qualitative Risk AnalysisCorrect

Perform Qualitative Risk Analysis prioritizes identified risks by assessing their probability of occurrence and potential impact on project objectives.

DPlan Risk ResponsesCorrect

Plan Risk Responses develops strategies and actions to address prioritized risks, either reducing threats or enhancing opportunities.

EEstimate Risk Activity Resources

Estimate Risk Activity Resources is not a standard risk management process; resource estimation belongs to the project resource management knowledge area.

Concept tested: PMBOK standard risk management processes identification

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management Processes#PMBOK#Project Management Knowledge Areas

Community Discussion

No community discussion yet for this question.

Full CAPM Practice