nerdexam
PMIPMI

CAPM · Question #487

CAPM Question #487: Real Exam Question with Answer & Explanation

The correct answer is B: Resource management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client's project manager. The technical lead is requesting two new developers. Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

Options

  • ABusiness management plan
  • BResource management plan
  • CCost management plan
  • DStakeholder engagement plan

Topics

#Resource Management#Project Planning#Roles and Responsibilities#Acquiring Resources

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions