CAPM · Question #487
CAPM Question #487: Real Exam Question with Answer & Explanation
The correct answer is B: Resource management plan. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client's project manager. The technical lead is requesting two new developers. Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?
Options
- ABusiness management plan
- BResource management plan
- CCost management plan
- DStakeholder engagement plan
Topics
#Resource Management#Project Planning#Roles and Responsibilities#Acquiring Resources