nerdexam
PMIPMI

CAPM · Question #486

CAPM Question #486: Real Exam Question with Answer & Explanation

The correct answer is A: -8. See the full explanation below for the reasoning.

Predictive Plan-Based Methodologies

Question

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Options

  • A-8
  • B1.4
  • C425
  • D8

Topics

#Earned Value Management (EVM)#Variance Analysis#Project Cost Management#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions