PMIPMI
CAPM · Question #486
CAPM Question #486: Real Exam Question with Answer & Explanation
The correct answer is A: -8. See the full explanation below for the reasoning.
Predictive Plan-Based Methodologies
Question
If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?
Options
- A-8
- B1.4
- C425
- D8
Topics
#Earned Value Management (EVM)#Variance Analysis#Project Cost Management#Performance Measurement
Community Discussion
No community discussion yet for this question.