nerdexam
PMI

CAPM · Question #486

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

The correct answer is A. -8. VAC (Variance at Completion) is calculated as BAC minus EAC. A negative result indicates the project is expected to finish over budget.

Predictive Plan-Based Methodologies

Question

If the estimate at completion (EAC) is 25, and the budget at completion (BAC) is 17, what is the variance at completion (VAC)?

Options

  • A-8
  • B1.4
  • C425
  • D8

How the community answered

(26 responses)
  • A
    85% (22)
  • B
    4% (1)
  • C
    8% (2)
  • D
    4% (1)

Why each option

VAC (Variance at Completion) is calculated as BAC minus EAC. A negative result indicates the project is expected to finish over budget.

A-8Correct

VAC = BAC - EAC = 17 - 25 = -8. The negative value signals a cost overrun, meaning the project is projected to spend 8 units more than originally budgeted. This is a standard earned value management formula.

B1.4

1.4 approximates the Cost Performance Index (CPI = EV/AC), which measures cost efficiency, not variance at completion.

C425

425 does not correspond to any recognized earned value management formula applied to these inputs.

D8

8 is the absolute magnitude of the difference but omits the negative sign; since EAC exceeds BAC, the variance must be negative to correctly indicate overrun.

Concept tested: Earned value management - Variance at Completion formula

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Earned Value Management (EVM)#Variance Analysis#Project Cost Management#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full CAPM Practice