nerdexam
PMIPMI

CAPM · Question #485

CAPM Question #485: Real Exam Question with Answer & Explanation

The correct answer is B: Use of established templates. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three.)

Options

  • ACollocated project teams
  • BUse of established templates
  • CMany expected simple scope change requests
  • DFew expected simple scope change requests
  • ERoutine and repetitive activities

Topics

#Traditional Project Management#Predictive Life Cycle#Linear Approach#Project Characteristics

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions