PMIPMI
CAPM · Question #485
CAPM Question #485: Real Exam Question with Answer & Explanation
The correct answer is B: Use of established templates. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three.)
Options
- ACollocated project teams
- BUse of established templates
- CMany expected simple scope change requests
- DFew expected simple scope change requests
- ERoutine and repetitive activities
Topics
#Traditional Project Management#Predictive Life Cycle#Linear Approach#Project Characteristics
Community Discussion
No community discussion yet for this question.