nerdexam
PMI

CAPM · Question #485

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project

The correct answer is B. Use of established templates D. Few expected simple scope change requests E. Routine and repetitive activities. Linear (predictive/waterfall) delivery is characterized by well-defined scope upfront and structured, repeatable work. Use of established templates (B) is typical because traditional projects follow standardized, documented processes. Few expected simple scope change requests (D)

Predictive, Plan-Based Methodologies

Question

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three.)

Options

  • ACollocated project teams
  • BUse of established templates
  • CMany expected simple scope change requests
  • DFew expected simple scope change requests
  • ERoutine and repetitive activities

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    92% (47)
  • C
    6% (3)

Explanation

Linear (predictive/waterfall) delivery is characterized by well-defined scope upfront and structured, repeatable work. Use of established templates (B) is typical because traditional projects follow standardized, documented processes. Few expected simple scope change requests (D) reflects the predictive nature - scope is fully defined at the start and change is deliberately minimized. Routine and repetitive activities (E) suit a linear approach because the work is predictable enough to plan sequentially. Collocated teams (A) are not specific to linear delivery - both agile and traditional teams can be collocated. Many scope changes (C) is the opposite of linear delivery's defining trait.

Topics

#Traditional Project Management#Predictive Life Cycle#Linear Approach#Project Characteristics

Community Discussion

No community discussion yet for this question.

Full CAPM Practice