nerdexam
PMIPMI

CAPM · Question #484

CAPM Question #484: Real Exam Question with Answer & Explanation

The correct answer is C: Work in progress. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team's workflow at any moment, the project manager will need to restrict the maximum amount of activities to be performed. Which element will the project manager handle?

Options

  • ACapacity limit
  • BFull system
  • CWork in progress
  • DVirtual board

Topics

#Kanban#WIP limits#Flow management#Agile methodologies

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions