CAPM · Question #484
A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team's workflow at any moment, the project manager will need to restrict the maximum a
The correct answer is C. Work in progress. Work in Progress (WIP) limits (C) are a foundational Kanban concept. They define the maximum number of work items allowed in any column (stage) of the Kanban board at one time, preventing bottlenecks and overloading the team. Restricting WIP is the primary mechanism Kanban uses t
Question
Options
- ACapacity limit
- BFull system
- CWork in progress
- DVirtual board
How the community answered
(61 responses)- A5% (3)
- B2% (1)
- C84% (51)
- D10% (6)
Explanation
Work in Progress (WIP) limits (C) are a foundational Kanban concept. They define the maximum number of work items allowed in any column (stage) of the Kanban board at one time, preventing bottlenecks and overloading the team. Restricting WIP is the primary mechanism Kanban uses to control workflow capacity. 'Capacity limit' (A) is not standard Kanban terminology. 'Full system' (B) is not a Kanban term. A 'virtual board' (D) refers to the digital representation of the Kanban board itself, not the constraint on workflow volume.
Topics
Community Discussion
No community discussion yet for this question.