nerdexam
PMIPMI

CAPM · Question #483

CAPM Question #483: Real Exam Question with Answer & Explanation

The correct answer is C: -4. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Calculate the cost variance, given the following: EV = 19 and AC = 23

Options

  • A42
  • B4
  • C-4
  • D1.22

Topics

#Cost Variance#Earned Value Management#Project Cost Management#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions