PMIPMI
CAPM · Question #483
CAPM Question #483: Real Exam Question with Answer & Explanation
The correct answer is C: -4. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Calculate the cost variance, given the following: EV = 19 and AC = 23
Options
- A42
- B4
- C-4
- D1.22
Topics
#Cost Variance#Earned Value Management#Project Cost Management#Performance Measurement
Community Discussion
No community discussion yet for this question.