PMIPMI
CAPM · Question #495
CAPM Question #495: Real Exam Question with Answer & Explanation
The correct answer is C: Held regular meetings more often with team members to check on their progress and obstacles. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming. What should the project manager have done to avoid this situation?
Options
- ACoupled unexperienced team members with individuals having extensive knowledge in the required field
- BHad open and transparent planning that engages internal and external stakeholders
- CHeld regular meetings more often with team members to check on their progress and obstacles
- DDiversified more of the project team to capture a broad range of experiences
Topics
#Team Performance Management#Communication Management#Monitoring & Controlling#Issue Prevention
Community Discussion
No community discussion yet for this question.