nerdexam
PMIPMI

CAPM · Question #495

CAPM Question #495: Real Exam Question with Answer & Explanation

The correct answer is C: Held regular meetings more often with team members to check on their progress and obstacles. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming. What should the project manager have done to avoid this situation?

Options

  • ACoupled unexperienced team members with individuals having extensive knowledge in the required field
  • BHad open and transparent planning that engages internal and external stakeholders
  • CHeld regular meetings more often with team members to check on their progress and obstacles
  • DDiversified more of the project team to capture a broad range of experiences

Topics

#Team Performance Management#Communication Management#Monitoring & Controlling#Issue Prevention

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions