CAPM · Question #496
The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?
The correct answer is D. Average velocity and cycle time. In adaptive (agile) projects, average velocity and cycle time together provide the metrics needed to forecast project completion by quantifying throughput rate and per-item delivery duration.
Question
Options
- ARisk burnup and control chart
- BCustomer satisfaction index and workload
- CAverage burndown and velocity
- DAverage velocity and cycle time
How the community answered
(57 responses)- A18% (10)
- B7% (4)
- C5% (3)
- D70% (40)
Why each option
In adaptive (agile) projects, average velocity and cycle time together provide the metrics needed to forecast project completion by quantifying throughput rate and per-item delivery duration.
Risk burnup and control charts track risk exposure trends and process stability respectively, not the pace of work delivery needed to forecast project completion.
Customer satisfaction index and workload measure quality perception and capacity usage, not the delivery throughput metrics required to predict how long the project will take.
Average burndown shows remaining work decreasing over time but does not include cycle time, which is essential for predicting the speed at which individual backlog items will be completed.
Average velocity measures how much work a team completes per iteration, enabling a forecast of how many iterations remain to finish the backlog. Cycle time measures the average elapsed time from when a work item is started to when it is done, providing insight into the pace of delivery and helping predict remaining project duration.
Concept tested: Agile project completion forecasting using velocity and cycle time
Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/agile
Topics
Community Discussion
No community discussion yet for this question.