PMIPMI
CAPM · Question #496
CAPM Question #496: Real Exam Question with Answer & Explanation
The correct answer is D: Average velocity and cycle time. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?
Options
- ARisk burnup and control chart
- BCustomer satisfaction index and workload
- CAverage burndown and velocity
- DAverage velocity and cycle time
Topics
#Adaptive Project Management#Project Forecasting#Agile Metrics#Velocity and Cycle Time
Community Discussion
No community discussion yet for this question.