nerdexam
PMIPMI

CAPM · Question #496

CAPM Question #496: Real Exam Question with Answer & Explanation

The correct answer is D: Average velocity and cycle time. See the full explanation below for the reasoning.

Adaptive Frameworks/Methodologies

Question

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

Options

  • ARisk burnup and control chart
  • BCustomer satisfaction index and workload
  • CAverage burndown and velocity
  • DAverage velocity and cycle time

Topics

#Adaptive Project Management#Project Forecasting#Agile Metrics#Velocity and Cycle Time

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions