nerdexam
PMI

CAPM · Question #496

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

The correct answer is D. Average velocity and cycle time. In adaptive (agile) projects, average velocity and cycle time together provide the metrics needed to forecast project completion by quantifying throughput rate and per-item delivery duration.

Adaptive Frameworks/Methodologies

Question

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

Options

  • ARisk burnup and control chart
  • BCustomer satisfaction index and workload
  • CAverage burndown and velocity
  • DAverage velocity and cycle time

How the community answered

(57 responses)
  • A
    18% (10)
  • B
    7% (4)
  • C
    5% (3)
  • D
    70% (40)

Why each option

In adaptive (agile) projects, average velocity and cycle time together provide the metrics needed to forecast project completion by quantifying throughput rate and per-item delivery duration.

ARisk burnup and control chart

Risk burnup and control charts track risk exposure trends and process stability respectively, not the pace of work delivery needed to forecast project completion.

BCustomer satisfaction index and workload

Customer satisfaction index and workload measure quality perception and capacity usage, not the delivery throughput metrics required to predict how long the project will take.

CAverage burndown and velocity

Average burndown shows remaining work decreasing over time but does not include cycle time, which is essential for predicting the speed at which individual backlog items will be completed.

DAverage velocity and cycle timeCorrect

Average velocity measures how much work a team completes per iteration, enabling a forecast of how many iterations remain to finish the backlog. Cycle time measures the average elapsed time from when a work item is started to when it is done, providing insight into the pace of delivery and helping predict remaining project duration.

Concept tested: Agile project completion forecasting using velocity and cycle time

Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/agile

Topics

#Adaptive Project Management#Project Forecasting#Agile Metrics#Velocity and Cycle Time

Community Discussion

No community discussion yet for this question.

Full CAPM Practice