PMIPMI
CAPM · Question #453
CAPM Question #453: Real Exam Question with Answer & Explanation
The correct answer is C: Perform Integrated Change Control. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project team identifies defects that will require a modification to a tool's functionality. What process should the project manager follow to obtain stakeholder buy-in?
Options
- AControl Schedule
- BPerform Qualitative Risk Analysis
- CPerform Integrated Change Control
- DControl Scope
Topics
#Change Control#Integrated Change Control#Project Management Processes
Community Discussion
No community discussion yet for this question.