nerdexam
PMIPMI

CAPM · Question #453

CAPM Question #453: Real Exam Question with Answer & Explanation

The correct answer is C: Perform Integrated Change Control. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project team identifies defects that will require a modification to a tool's functionality. What process should the project manager follow to obtain stakeholder buy-in?

Options

  • AControl Schedule
  • BPerform Qualitative Risk Analysis
  • CPerform Integrated Change Control
  • DControl Scope

Topics

#Change Control#Integrated Change Control#Project Management Processes

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions