nerdexam
PMIPMI

CAPM · Question #454

CAPM Question #454: Real Exam Question with Answer & Explanation

The correct answer is C: Exit criteria. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What key component of the project charter defines the conditions for dosing a project phase?

Options

  • APurpose
  • BApproval requirements
  • CExit criteria
  • DHigh-level requirements

Topics

#Project Charter#Exit Criteria#Phase Closure#Project Initiation

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions