CAPM · Question #459

A project manager joined a company to replace someone that left the project. There was no hand over, but the previous project manager developed a detailed schedule for the project team completed…

The correct answer is A. Adaptive project management. Adaptive project management is correct because the scenario presents multiple uncertainty factors: no formal handover (knowledge gaps), a distributed team (communication challenges), and junior team members (varying skill levels). Adaptive methods allow the incoming PM to…

Adaptive Frameworks/Methodologies

Question

A project manager joined a company to replace someone that left the project. There was no hand over, but the previous project manager developed a detailed schedule for the project team completed some project deliverables. The team is not collocated and some of the team members are former interns that were recently employed full time. What is the most suitable project delivery method?

Options

  • AAdaptive project management
  • BLinear project management
  • CExtreme project management
  • DIntegrated project management

How the community answered

(46 responses)
  • A
    63% (29)
  • B
    4% (2)
  • C
    13% (6)
  • D
    20% (9)

Explanation

Adaptive project management is correct because the scenario presents multiple uncertainty factors: no formal handover (knowledge gaps), a distributed team (communication challenges), and junior team members (varying skill levels). Adaptive methods allow the incoming PM to assess the current state incrementally, course-correct as they learn the project, and build team capability through iterative cycles rather than rigid execution of an inherited plan.

B (Linear/Waterfall) is wrong because it assumes stable requirements, a clear upfront plan, and a knowledgeable team - none of which are present here. While a schedule exists, the PM has no context to trust or execute it reliably without handover.

C (Extreme project management) is wrong because XPM is designed for highly chaotic, R&D-style projects where even the goal is uncertain. This project has defined deliverables and an existing schedule, so it's not extreme - just disrupted.

D (Integrated project management) is wrong because it refers to coordinating PM processes across an organization or program, not a delivery methodology for a single project in transition.

Memory tip: When you see new PM + no handover + dispersed/inexperienced team, think "ADAPT to fill the gaps." Adaptive thrives on uncertainty and supports discovery-based execution - perfect when you inherit a project blind.

Topics

#Adaptive Project Management#Team Composition#Delivery Method Selection#Project Transition