CAPM · Question #459
A project manager joined a company to replace someone that left the project. There was no hand over, but the previous project manager developed a detailed schedule for the project team completed…
The correct answer is A. Adaptive project management. Adaptive project management is correct because the scenario presents multiple uncertainty factors: no formal handover (knowledge gaps), a distributed team (communication challenges), and junior team members (varying skill levels). Adaptive methods allow the incoming PM to…
Question
Options
- AAdaptive project management
- BLinear project management
- CExtreme project management
- DIntegrated project management
How the community answered
(46 responses)- A63% (29)
- B4% (2)
- C13% (6)
- D20% (9)
Explanation
Adaptive project management is correct because the scenario presents multiple uncertainty factors: no formal handover (knowledge gaps), a distributed team (communication challenges), and junior team members (varying skill levels). Adaptive methods allow the incoming PM to assess the current state incrementally, course-correct as they learn the project, and build team capability through iterative cycles rather than rigid execution of an inherited plan.
B (Linear/Waterfall) is wrong because it assumes stable requirements, a clear upfront plan, and a knowledgeable team - none of which are present here. While a schedule exists, the PM has no context to trust or execute it reliably without handover.
C (Extreme project management) is wrong because XPM is designed for highly chaotic, R&D-style projects where even the goal is uncertain. This project has defined deliverables and an existing schedule, so it's not extreme - just disrupted.
D (Integrated project management) is wrong because it refers to coordinating PM processes across an organization or program, not a delivery methodology for a single project in transition.
Memory tip: When you see new PM + no handover + dispersed/inexperienced team, think "ADAPT to fill the gaps." Adaptive thrives on uncertainty and supports discovery-based execution - perfect when you inherit a project blind.