PMIPMI
CAPM · Question #459
CAPM Question #459: Real Exam Question with Answer & Explanation
The correct answer is A: Adaptive project management. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
A project manager joined a company to replace someone that left the project. There was no hand over, but the previous project manager developed a detailed schedule for the project team completed some project deliverables. The team is not collocated and some of the team members are former interns that were recently employed full time. What is the most suitable project delivery method?
Options
- AAdaptive project management
- BLinear project management
- CExtreme project management
- DIntegrated project management
Topics
#Project delivery methods#Adaptive approaches#Team integration#Uncertainty management
Community Discussion
No community discussion yet for this question.