CAPM · Question #478
A Scrumban team member wants to know what work has been completed this week. Which chart should the team member review?
The correct answer is D. Burndown chart. A burndown chart (D) tracks the amount of work remaining (or completed) over time, making it ideal for seeing how much work was finished within a specific period like a week. Scrumban blends Scrum and Kanban, and the burndown chart is the standard Scrum-derived artifact for…
Question
Options
- AGantt chart
- BFeature chart
- CKanban chart
- DBurndown chart
How the community answered
(42 responses)- A5% (2)
- C2% (1)
- D93% (39)
Explanation
A burndown chart (D) tracks the amount of work remaining (or completed) over time, making it ideal for seeing how much work was finished within a specific period like a week. Scrumban blends Scrum and Kanban, and the burndown chart is the standard Scrum-derived artifact for tracking progress and completion. A Gantt chart (A) shows scheduled timelines, not completion rates. A 'feature chart' (B) is not a standard project management artifact. A Kanban board (C) shows the current state of work items but does not historically track what was completed over a time window.
Topics
Community Discussion
No community discussion yet for this question.