CAPM · Question #479
In which project performance domain is the work breakdown structure (WBS) developed?
The correct answer is D. Planning. According to PMBOK 7th Edition, the Planning performance domain (D) covers all activities related to organizing and decomposing project scope, schedule, budget, and resources - this is where the WBS is created as a scope decomposition tool. The Delivery domain (A) focuses on…
Question
Options
- ADelivery performance
- BProject work
- CDevelopment approach and life cycle
- DPlanning
How the community answered
(44 responses)- A5% (2)
- B7% (3)
- C2% (1)
- D86% (38)
Explanation
According to PMBOK 7th Edition, the Planning performance domain (D) covers all activities related to organizing and decomposing project scope, schedule, budget, and resources - this is where the WBS is created as a scope decomposition tool. The Delivery domain (A) focuses on meeting requirements and producing deliverables. The Project Work domain (B) covers establishing and managing project processes and physical resources. The Development Approach and Life Cycle domain (C) determines whether the project uses predictive, agile, or hybrid methods - it does not produce the WBS itself.
Topics