nerdexam
PMIPMI

CAPM · Question #499

CAPM Question #499: Real Exam Question with Answer & Explanation

The correct answer is C: Develop a release plan with milestones for major features.. See the full explanation below for the reasoning.

Adaptive Frameworks/Methodologies

Question

A project sponsor has requested a clear delivery roadmap for the implementation of a complex system that does not have clear and stable requirements. How should the team address the project sponsor's request?

Options

  • ADevelop a product backlog with all the required user stories.
  • BDevelop a project schedule with sufficient lag between tasks.
  • CDevelop a release plan with milestones for major features.
  • DDevelop a prototype to determine the delivery time required.

Topics

#Release Planning#Adaptive Planning#Unstable Requirements#Project Roadmapping

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions