- Question #109Schedule Planning and Development
You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your p...
milestone listschedule artifactsproject documentationproject charter - Question #110Schedule Monitoring and Controlling
Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement...
records management systemcontract managementprocurement documentationadminister procurements - Question #111Schedule Monitoring and Controlling
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled t...
cost performance indexearned value managementCPI calculationproject performance metrics - Question #112Schedule Planning and Development
Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of...
resource calendaractivity duration estimatingweak matrixshared resources - Question #113Schedule Planning and Development
You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on t...
staffing management planresource acquisitionhuman resource planningteam management - Question #114Stakeholder Communication
Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence ove...
stakeholder analysis matrixstakeholder influencestakeholder intereststakeholder identification - Question #115Schedule Planning and Development
You are the project manager for your organization. Your project will need four electrical engineers for the project though there are no electrical engineers within your department....
resource requirementsresource planningactivity resource estimatingproject constraints - Question #116Schedule Monitoring and Controlling
Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorpor...
scope baselinescope change managementchange integrationactivity list updates - Question #117Schedule Monitoring and Controlling
You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure dep...
cost varianceearned value managementCV interpretationschedule performance - Question #118Schedule Planning and Development
You are the project manager for your organization. You are working with your project team to define the project network diagram. Several of the activities in the project schedule a...
dependency determinationexternal dependenciesnetwork diagramschedule development - Question #119Schedule Planning and Development
You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule...
critical path methodnetwork diagramCPM analysisschedule logic - Question #120Schedule Planning and Development
You are the project manager for your organization. Management has offered you a bonus if you can complete the project work two months earlier than what your schedule predicts. You...
fast trackingschedule compressioncrashingcost-neutral compression - Question #121Schedule Monitoring and Controlling
In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?
control scheduleschedule management processesPMBOK time managementprocess effort - Question #122Stakeholder Communication
Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of...
communication channels formulastakeholder countcommunication planningn(n-1)/2 - Question #123Schedule Planning and Development
You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will creat...
develop schedule outputsschedule baselinePMBOK process outputsschedule development - Question #124Stakeholder Communication
You are the project manager of the NDF project. You need to determine how often a complete project report can be made, including forecasted project completion information for your...
performance reportingreporting frequencyschedule forecastingproject status reports - Question #125Schedule Monitoring and Controlling
You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based o...
planned valueearned value managementPV calculationschedule performance baseline - Question #126Schedule Monitoring and Controlling
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project,...
TCPIto-complete performance indexearned value forecastingschedule cost analysis - Question #127Schedule Monitoring and Controlling
You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output o...
control schedule outputswork performance measurementsPMBOK inputs outputsschedule control - Question #128Stakeholder Communication
You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your pr...
performance reportingschedule variance communicationexceptions reportingstakeholder updates - Question #129Schedule Monitoring and Controlling
You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete t...
planned valueearned value managementEVM formulaschedule performance - Question #130Schedule Planning and Development
You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holdi...
PERTthree-point estimatingactivity duration estimatingestimating formula - Question #131Schedule Planning and Development
Choose and reorder the essential steps required in developing the baseline schedule. Select an item from the right pane. Click button to move the selected item to the left pane. Cl...
baseline scheduleschedule development processschedule planning stepsproject planning - Question #132Schedule Planning and Development
Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although som...
critical path methodfloatschedule risknetwork diagram - Question #133Schedule Monitoring and Controlling
You work as a Project Manager for Tech Perfect Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: What will be...
cost varianceearned value managementEVM formulaschedule performance - Question #134Schedule Monitoring and Controlling
Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though sh...
estimate to completeearned value managementschedule forecastingEVM indices - Question #135Schedule Monitoring and Controlling
Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the followi...
risk ownerrisk response implementationcontingency planroles and responsibilities - Question #136Schedule Monitoring and Controlling
Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen. If this event does happen, how much will Donna have left...
contingency reserverisk analysisexpected monetary valuerisk quantification - Question #137Schedule Monitoring and Controlling
John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion. When John fast...
fast trackingschedule compressionrisk registerschedule recovery - Question #138Schedule Planning and Development
You are the project manager of the NHQ Project and are trying to determine which seller you should choose for the project. You have received proposals from six vendors and they are...
source selectionweighting systemvendor evaluationprocurement planning - Question #139Schedule Planning and Development
Frank is the project manager in BlueWell Inc. He is working with his project to subdivide the project work packages into smaller, more manageable components. He and the project tea...
decompositionactivity definitionwork packagesWBS - Question #140Schedule Planning and Development
Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project...
critical chain methodresource availabilityresource constraintsschedule network - Question #141Schedule Planning and Development
Mary is the project manager for her organization. She is working with the project team to define the project activities. She is concerned about some of the dependencies of the proj...
project constraintsmandatory dependencyexternal constraintschedule dependencies - Question #142Schedule Planning and Development
You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?
sequence activitiesproject schedule network diagramprocess outputsactivity sequencing - Question #143Schedule Monitoring and Controlling
Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and sh...
schedule varianceearned value managementEVM formulaschedule performance - Question #144Schedule Planning and Development
Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration proc...
organizational process assetsanalogous estimatinghistorical informationduration estimating - Question #145Stakeholder Communication
Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method t...
power interest gridstakeholder classificationstakeholder analysiscommunication planning - Question #146Schedule Monitoring and Controlling
You work as the project manager for BlueWell Inc. You are reviewing and regulating the progress to meet the performance objectives defined in the project management plan. Mark, a t...
monitor and controlperformance reportprocess inputsproject management plan - Question #147Schedule Monitoring and Controlling
You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most...
fast trackingschedule compressionactivity overlapschedule management - Question #148Schedule Planning and Development
Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspector...
external dependenciesdependency typesactivity sequencingmandatory dependency - Question #149Stakeholder Communication
Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are...
communication typesformal/informal communicationinternal/external communicationstakeholder communication - Question #150Schedule Planning and Development
Frank is the project manager of a construction project. In this project, Frank has elected to allow the interior design phase of the project to overlap with the pool construction p...
fast trackingschedule compressionphase overlapschedule planning - Question #151Schedule Monitoring and Controlling
You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $...
CPIearned value managementcost performance indexschedule performance - Question #152Schedule Planning and Development
You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or...
make-or-buy analysisprocurementoutsourcingbuild vs buy - Question #153Schedule Planning and Development
You work as a project manager for BlueWell Inc. You have to identify the specific actions to be performed to produce the project deliverables. For this, you have to explain the thr...
define activitiesschedule inputsscope baselineWBS - Question #154Schedule Planning and Development
Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project p...
resource levelingcrashingschedule compressionresource constraints - Question #155Schedule Planning and Development
Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the network diagram, find out which path is the...
critical path methodnetwork diagrampath analysisCPM - Question #156Schedule Monitoring and Controlling
Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.
project integration managementintegrated change controlPMBOK knowledge areasproject plan execution - Question #157Schedule Planning and Development
Don is the project manager of the NQP project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have governme...
activity attributesactivity listregulatory complianceschedule documentation - Question #158Schedule Monitoring and Controlling
You are the project manager for your organization. You have been recording the actual results of activity duration for your project. Many of the results are late and this is causin...
schedule network analysiswhat-if scenariosschedule controlmilestone alignment