PMI-SP · Question #121
In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?
The correct answer is C. Control schedule. Of all six processes, the control schedule process will take the majority of the time in the project time management knowledge area. Control schedule process is a method of monitoring the status of the project to update project progress and deal with the changes to the schedule…
Question
In the project time management knowledge area, there are six processes. According to the PMBOK, which project time knowledge area will have the majority of the effort?
Options
- AEstimate activity resources
- BDefine activities
- CControl schedule
- DDevelop schedule
How the community answered
(21 responses)- A5% (1)
- C90% (19)
- D5% (1)
Explanation
Of all six processes, the control schedule process will take the majority of the time in the project time management knowledge area. Control schedule process is a method of monitoring the status of the project to update project progress and deal with the changes to the schedule baseline. It is concerned with: Determining the current status of the project Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur Control schedule is a component of the Perform Integration Change Control process. Answer options B, A, and D are incorrect. These processes will not take the longest to complete.