PMI
PMI-SP · Question #72
PMI-SP Question #72: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #72. The question stem and answer options stay visible for context.
Question
You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?
Options
- AIncrease the duration estimates for each activity.
- BDiscipline the project team.
- CIt is method of identifying and eliminating the causes of a problem, thus preventing their
- DCorrective actions.
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.