nerdexam
PMI

PMI-SP · Question #212

PMI-SP Question #212: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #212. The question stem and answer options stay visible for context.

Question

Holly is the project manager for her organization. Her current project is running late and her project customer has asked Holly to find a method to apply corrective actions to the project schedule. Holly is exploring the concept of crashing the project. Which of the following statements is true about crashing the activities in Holly's project?

Options

  • AThe activities to be crashed must have additional quality control metrics associated with them.
  • BThe activities to be crashed cannot be of fixed duration.
  • CThe activities to be crashed cannot have risks associated with them greater than 0.80.
  • DThe activities cannot be on the critical path in order to be crashed.

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice