nerdexam
PMI

PMI-SP · Question #266

Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below: MeasurementsValues BCWP (or EV) 425 BCWS (o

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #266. The question stem and answer options stay visible for context.

Schedule Monitoring and Controlling

Question

Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below:

MeasurementsValues BCWP (or EV) 425 BCWS (or PV) 400 ACWP (or AC) 510 What is the schedule performance index (SPI) of the project at the current point of time?

Options

  • A1.082
  • B0.88
  • C1.0625
  • D0.96

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#SPI#schedule performance index#EVM#earned value
Full PMI-SP Practice