Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below: MeasurementsValues BCWP (or EV) 425 BCWS…

The correct answer is C. 1.0625. According to the question, you are required to calculate the schedule performance index (SPI) of the project. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of…

Schedule Monitoring and Controlling

Question

Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below:

MeasurementsValues BCWP (or EV) 425 BCWS (or PV) 400 ACWP (or AC) 510 What is the schedule performance index (SPI) of the project at the current point of time?

Options

  • A1.082
  • B0.88
  • C1.0625
  • D0.96

How the community answered

(22 responses)
  • B
    5% (1)
  • C
    95% (21)

Explanation

According to the question, you are required to calculate the schedule performance index (SPI) of the project. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula: SPI = Earned Value (EV) / Planned Value (PV) If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target. Here, SPI is calculated as follows: SPI = EV / PV = 425/400 = 1.0625 As the SPI (1.0625) is greater than 1, it shows that the schedule performance is better than expected. What is BCWP (or EV)? Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is the budgeted amount for the work actually completed on the schedule activity during a given time period. What is BCWS (or PV)? Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component. What is ACWP (or AC)? Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity. It is the cost of the work to date, including direct and indirect AC is money that has actually been expended to date.

Topics

#SPI#schedule performance index#EVM#earned value