nerdexam
PMI

PMI-SP · Question #239

PMI-SP Question #239: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #239. The question stem and answer options stay visible for context.

Question

You are the project manager for GGY Project. You are working with your project team to record the actual durations for the activities they have completed in the project schedule. Mary, one of your project team members, wants to know why you need to know how long it actually took the project team to complete their assignments as long as the project work is completed. Which of the following is the best response for Mary's query?

Options

  • AActual durations need to be recorded to track process improvement.
  • BActual durations need to be recorded to create the schedule baseline.
  • CActual durations need to be recorded to measure the actual progress of the project.
  • DActual durations need to be recorded to perform quality control on the project management

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice