PMI-SP · Question #5
Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the…
The correct answer is A. It is not good news because a larger number means the schedule duration estimates were. Cost and schedule performance indexes should be as close to 1 as possible. A larger value, such as 2.12, means that the schedule duration estimates were likely bloated or incorrect to begin with. Answer option B is incorrect. This is not the best choice for this question…
Question
Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?
Options
- AIt is not good news because a larger number means the schedule duration estimates were
- BThey likely do not understand the SPI formula.
- CIt is not good news, as the number should be closer to 100 than 0.
- DIt is good news, but Mark may have large cost variances to achieve this value.
How the community answered
(63 responses)- A60% (38)
- B6% (4)
- C11% (7)
- D22% (14)
Explanation
Cost and schedule performance indexes should be as close to 1 as possible. A larger value, such as 2.12, means that the schedule duration estimates were likely bloated or incorrect to begin with. Answer option B is incorrect. This is not the best choice for this question. Answer option C is incorrect. The number should not be close to 100; it should be close to 1. Answer option D is incorrect. While Mark may have crashed the schedule and driven up costs to achieve the SPI value, a more likely reason is that the time estimates were bloated.