nerdexam
PMI

PMI-SP · Question #6

You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure: Mary, a project team member, reports that an identified risk is likely to happen in the proje

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #6. The question stem and answer options stay visible for context.

Schedule Monitoring and Controlling

Question

You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:

Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

Exhibit

PMI-SP question #6 exhibit

Options

  • A32 days
  • B29 days
  • C27 days
  • D26 days

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#network diagram#critical path#risk impact#float analysis
Full PMI-SP Practice