PMI-SP · Question #6
PMI-SP Question #6: Real Exam Question with Answer & Explanation
The correct answer is D. 26 days. If Activity D increases by six days, the duration of the project will not change. There is 11 days of float available for Activity D so it may delay by six days without affecting the project end date. Float or total float (TF) is the total amount of time that a schedule activity
Question
Exhibit
Options
- A32 days
- B29 days
- C27 days
- D26 days
Explanation
If Activity D increases by six days, the duration of the project will not change. There is 11 days of float available for Activity D so it may delay by six days without affecting the project end date. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options A, B, and C are incorrect. These are not valid answers for the question.
Community Discussion
No community discussion yet for this question.