Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders…
The correct answer is B. Stakeholder register. According to the PMBOK, the main output of the identify stakeholders process is the stakeholder register. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the…
Question
Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?
Options
- ACommunications management plan
- BStakeholder register
- CRequirements
- DStakeholder management strategy
How the community answered
(50 responses)- A2% (1)
- B94% (47)
- D4% (2)
Explanation
According to the PMBOK, the main output of the identify stakeholders process is the stakeholder register. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project. Answer option A is incorrect. The communications management plan is an output of communications Answer option D is incorrect. The stakeholder management strategy is an output of stakeholder identification, but it is not the main output. Answer option C is incorrect. Requirements are not an output of the stakeholder identification